[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107758,783,1,"单选题","实行工程量清单计价的工程，应当采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单价合同",true,{"key":16,"text":17,"correct":18},"B","综合单价合同",false,{"key":20,"text":21,"correct":18},"C","总价合同",{"key":23,"text":24,"correct":18},"D","成本加酬金合同","考点:合同价款约定内容。实行工程量清单计价的工程，应采用单价合同；建设规模较小，技术难度较低，工期较短，且施工图设计已审查批准的建设工程可采用总价合同；紧急抢险、救灾以及施工技术特别复杂的建设工程可采用成本加酬金合同。参见教材P151。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]