[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107755,783,1,"单选题","根据《计价规范》规定，在其他项目清单中，应包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","环境保护费",false,{"key":16,"text":17,"correct":14},"B","夜间施工费",{"key":19,"text":20,"correct":14},"C","施工排水费",{"key":22,"text":23,"correct":24},"D","暂估价",true,"考点:工程量清单编制。其他项目清单是指因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量的清单。包括暂列金额、暂估价、计日工、总承包服务费。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]