[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107754,783,1,"单选题","某土方工程《建设工程工程量清单计价规范》签订了单价合同，招标清单中土方开挖工程量为8000m3，施工过程中承包人采用了放坡的开挖方式，完工计量时，承包人因放坡增加土方开挖量1000m3，因工作面增加土方开挖量1600m3，因施工操作不慎造成塌方增加的土方开挖量500m3，则应予结算的土方开挖工程量为（ ）m3。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","11100",false,{"key":16,"text":17,"correct":14},"B","10600",{"key":19,"text":20,"correct":14},"C","9000",{"key":22,"text":23,"correct":24},"D","8000",true,"考点:工程量清单编制。分部分项工程量清单应按《建设工程工程量清单计价规范》GB50500—2013的规定，清单项目的工程量计算规则，其工程量是以形成工程实体为准，并以完成后的净值来计算的。参见教材P132。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]