[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107752,783,1,"单选题","采用成本加奖罚合同，当实际成本大于预期成本时，承包人可以得到（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程成本.酬金和预先约定的奖金",false,{"key":16,"text":17,"correct":14},"B","工程成本和预先约定的奖金，不能得到酬金",{"key":19,"text":20,"correct":14},"C","工程成本，但不能得到酬金和预先约定的奖金",{"key":22,"text":23,"correct":24},"D","工程成本和酬金，但也可能会处予一笔罚金",true,"考点:合同计价方式。实际成本＞预期成本，承包方可得到实际成本和酬金，但视实际成本高出预期成本的情况，被处以一笔罚金。参见教材P150。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]