[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107749,783,1,"单选题","下列关于单价合同的说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","单价合同的工程量清单内所列出的分部分项工程的工程量为准确工程量",false,{"key":16,"text":17,"correct":14},"B","执行单价合同，工程量及合同单价在合同实施过程中允许有浮动变化",{"key":19,"text":20,"correct":21},"C","单价合同结算时，以实际完成工程量为依据",true,{"key":23,"text":24,"correct":14},"D","采用单价合同，实际工程价格与合同价格必定一致","考点:合同计价方式。选项A，单价合同的工程量清单内所列出的分部分项工程的工程量为估计工程量，而非准确工程量；选项B，工程量在合同实施过程中允许有上下的浮动变化，但分部分项工程的合同单价却不变，结算支付时以实际完成工程量为依据；选项D，采用单价合同，实际工程价格与合同价格有可能不一致。参见教材P147。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]