[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107745,783,1,"单选题","某挖沟槽土方项目招标，工程量清单中的土方开挖工程量为200m3，投标人按施工方案计算得到的预算工程量为300m3，按企业定额该子项基价为100元\u002Fm3，则该土方开挖的单位报价应为（ ）元\u002Fm3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","300",false,{"key":16,"text":17,"correct":14},"B","200",{"key":19,"text":20,"correct":21},"C","150",true,{"key":23,"text":24,"correct":14},"D","100","考点:投标报价审核方法。在计算综合单价时，需要将增量费用分摊，进行组价，即由预算工程量乘以企业定额基价得出的总价应与清单工程量乘以综合单价得出的总价相等，300×100\u002F200=150（元\u002Fm3）。参见教材P144。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]