[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107744,783,1,"单选题","某多层砖混住宅工程的基础开挖土方工程量按照工程量计算规则计算的清单工程量为230立方，按照施工方案及工程量计算规则计算的定额工程量为450立方，定额单位为10立方，计算挖基础土方清单含量为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","19.565",false,{"key":16,"text":17,"correct":18},"B","0.196",true,{"key":20,"text":21,"correct":14},"C","0.511",{"key":23,"text":24,"correct":14},"D","0.051","考点:投标报价审查方法。挖基础土方清单数量=定额量\u002F清单量\u002F定额单位=450\u002F230\u002F10=0.196。参见教材P145。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]