[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107743,783,1,"单选题","根据《建设工程工程量清单计价规范》，关于投标人的投标总价编制的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","为降低投标总价，投标人可以将暂列金额降至零",false,{"key":16,"text":17,"correct":14},"B","投标总价可在分部分项工程费、措施项目费、其他项目费和规费，税金合计金额上做出优惠",{"key":19,"text":20,"correct":14},"C","开标前投标人来不及修改标书时，可在投标者致函中给出优惠比例，并将优惠后的总价作为新的投标价",{"key":22,"text":23,"correct":24},"D","投标人对投标报价的任何优惠均应反映在相应清单项目的综合单价中",true,"考点:投标报价审核方法。投标总价应与分部分项工程费、措施项目费、其他项目费和规费、税金的合计金额一致。即投标人在进行工程量清单招标的投标报价时，不能进行投标总价优惠（或降价、让利），投标人对投标报价的任何优惠（如降价、让利）均应反映在相应清单项目的综合单价中。参见教材P。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]