[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107742,783,1,"单选题","如果招标工程清单项目特征描述与设计图纸不符，投标人应以（ ）为准，确定投标报价的综合单价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标工程清单的项目特征描述",true,{"key":16,"text":17,"correct":18},"B","设计图纸的项目特征描述",false,{"key":20,"text":21,"correct":18},"C","设计变更的项目特征描述",{"key":23,"text":24,"correct":18},"D","实际施工的项目特征描述","考点:投标报价审核方法。如果招标工程清单项目特征描述与设计图纸不符，投标人应以招标（分部分项）工程清单项目特征描述为准，确定投标报价的综合单价；如果施工图纸或设计变更致使其项目特征与工程清单项目特征描述不一致，双方应按实际施工的项目特征，依据合同约定重新确定综合单价。参见教材P142。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]