[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107741,783,1,"单选题","工程量清单的十二位项目编码中，七至九位表示（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分类顺序码",false,{"key":16,"text":17,"correct":14},"B","专业工程码",{"key":19,"text":20,"correct":14},"C","分部工程顺序码",{"key":22,"text":23,"correct":24},"D","分项工程项目名称顺序码",true,"考点:工程量清单编制。项目编码是分部分项工程量清单项目名称的数字标识。在十二位数字中，一至二位为专业工程码，三至四位为附录分类顺序码，五至六位为分部工程顺序码，七、八、九位为分项工程项目名称顺序码，十至十二位为清单项目名称顺序码。参见教材P131。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]