[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107738,783,1,"单选题","根据《建设工程工程量清单计价规范》，分部分项工程项目清单中的分项工程项目名称顺序码的数位是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","三至四位",false,{"key":16,"text":17,"correct":14},"B","五至六位",{"key":19,"text":20,"correct":21},"C","七至九位",true,{"key":23,"text":24,"correct":14},"D","十至十二位","考点:工程量清单编制。在十二位数字中，一至二为专业工程码，三至四为附录分类顺序码，五至六位为分部工程顺序码。七、八、九位为分项工程项目名称顺序码，十至十二位为清单项目名称顺序码。参见教材P131。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]