[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107737,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500－2013），编制工程量清单时，计日工表中的人工应按（ ）列项。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工种",true,{"key":16,"text":17,"correct":18},"B","职称",false,{"key":20,"text":21,"correct":18},"C","职务",{"key":23,"text":24,"correct":18},"D","技术等级","考点:工程量清单编制。根据“计价规范”，编制其他项目清单时，计日工表中的人工应按工种，材料和机械应按规格、型号，详细列项。同时，应当留意招标人确定的暂列金额、暂估价。参见教材P133。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]