[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107735":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107735,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013的规定，关于编制招标控制价的说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","综合单价应包括由招标人承担的费用及风险",false,{"key":16,"text":17,"correct":14},"B","安全文明施工费按投标人的施工组织设计确定",{"key":19,"text":20,"correct":14},"C","措施项目费应为包括规费.税金在内的全部费用",{"key":22,"text":23,"correct":24},"D","暂估价中的材料单价，应按招标工程量清单的单价计入综合单价",true,"考点:招标控制价及确定方法。综合单价还应包括招标文件中划分的应由投标人承担的风险范围及其费用；若招标文件提供了暂估单价材料的，应按暂估的单价计入综合单价。安全文明施工费，应按照国家或省级、行业建设主管部门的规定标准计价。措施项目费应为包括除规费、税金外的全部费用。材料、设备的单价，按招标工程量清单中列出的单价，计入综合单价。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]