[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107733,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，下列有关招标控制价的编制说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标人应根据国家或省级.行业建设主管部门的规定标准对安全文明施工费计价",false,{"key":16,"text":17,"correct":18},"B","暂列金额按照工程量清单中列出的金额填写",true,{"key":20,"text":21,"correct":14},"C","招标人给出计日工的暂定数量，投标人填写单价",{"key":23,"text":24,"correct":14},"D","若国家税法发生变化或调整，招标人可以不对税金清单作出相应调整","考点:招标控制价及确定方法。选项A，招标人应根据国家或省级、行业建设主管部门的规定标准对安全文明施工费计价；选项C，编制招标控制价时，对计日工的人工单价和施工机械单价应按省级、行业建设主管部门或其授权的工程造价管理机构公布的单价计算；选项D，若国家税法发生变化或调整，招标人应对税金清单相应调整。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]