[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107732,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500-2013），关于工程量清单编制的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","综合单价包括应由招标人承担的全部风险费用",false,{"key":16,"text":17,"correct":14},"B","招标文件提供了暂估单价的材料，其材料费用应计入其他项目清单费",{"key":19,"text":20,"correct":14},"C","措施项目费包括规费、税金等在内",{"key":22,"text":23,"correct":24},"D","规费和税金必须按有关部门的规定计算，不得作为竞争性费用",true,"考点:工程量清单编制。选项A，综合单价还应包括招标文件中划分的应由投标人承担的风险范围及其费用；选项B，暂估价中的材料、工程设备单价、控制价应按招标工程量清单列出的单价计入综合单价；选项C，措施项目费=∑措施项目工程量×措施项目综合单价+∑单项措施费。参见教材P133～140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]