[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107730,783,1,"单选题","根据《计价规范》的规定，下列说法中错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","国有资金投资项目必须采用工程量清单计价",false,{"key":16,"text":17,"correct":14},"B","工程量清单是调整工程量、进行工程索赔的依据",{"key":19,"text":20,"correct":14},"C","不采用工程量清单计价的建设工程，应执行规范除工程量清单等专门规定外的其他规定",{"key":22,"text":23,"correct":24},"D","补充项目清单由工程造价管理机构编制",true,"考点:工程量清单概述。根据“计价规范”的规定，如果出现“计量规范”附录中未包括的项目，编制人应做补充，并报省级或行业工程造价管理机构备案。参见教材P129～131。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]