[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107729,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）中对招标控制价的有关规定，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标控制价公布后根据需要可以上浮或下调",false,{"key":16,"text":17,"correct":14},"B","招标人可以只公布招标控制价总价，也可以只公布单价",{"key":19,"text":20,"correct":14},"C","招标控制价可以在招标文件中公布，也可以在开标时公布",{"key":22,"text":23,"correct":24},"D","招标控制价报工程所在地工程造价管理机构备查",true,"考点:招标控制价及确定方法。选项AC，招标人应在招标文件中如实公布招标控制价，不得对所编制的招标控制价进行上浮或下调；选项B，招标人在招标文件中应公布招标控制价各组成部分的详细内容，不得只公布招标控制价总价。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]