[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107728,783,1,"单选题","关于编制最高投标限价时总承包服务费的可参考标准，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","招标人仅要求对分包专业工程进行总承包管理和协调时，按分包专业工程估算造价的0.5%计算",false,{"key":16,"text":17,"correct":14},"B","招标人仅要求对分包专业工程进行总承包管理和协调时，按分包专业工程估算造价的1%计算",{"key":19,"text":20,"correct":14},"C","招标人要求对分包专业工程进行总承包管理和协调，且要求提供配合服务时，按分包专业工程估算造价的1%～3%计算",{"key":22,"text":23,"correct":24},"D","招标人要求对分包专业工程进行总承包管理和协调，且要求提供配合服务时，按分包专业工程估算造价的3%～5%计算",true,"考点:招标控制价及确定方法。当招标人要求总包人对其发包的专业工程既进行总承包管理和协调，又要求提供相应配合服务时，总承包服务费根据招标文件列出的配合服务内容，按发包的专业工程估算造价的3%～5%计算。参见教材P140。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]