[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107725,783,1,"单选题","某工程原定2017年9月30日竣工，因承包人原因，致使工程延至2017年12月30日竣工。但在2017年10月因法律法规的变化导致工程造价增加100万元，则该工程合同价款的正确处理方式是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调增50万元",false,{"key":16,"text":17,"correct":14},"B","调增75万元",{"key":19,"text":20,"correct":14},"C","调增100万元",{"key":22,"text":23,"correct":24},"D","不予调增",true,"考点:法律法规变化。因承包人原因导致工期延误的，在合同工程原定竣工时间之后，合同价款调增的不予调整，合同价款调减的予以调整。参见教材P164。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]