[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107724,783,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500－2013，下列有关计日工的表述正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人完成发包人提出的工程合同范围以内的零星工作，以计日工的形式计价",false,{"key":16,"text":17,"correct":14},"B","发包人提交有计日工记录汇总的现场签证报告应一式三份",{"key":19,"text":20,"correct":21},"C","发包人应当在收到承包人提交现场签证报告后的2天内予以确认",true,{"key":23,"text":24,"correct":14},"D","发包人逾期未确认的现场签证报告，不应视为发包人认可","考点:计日工。选项A，承包人完成发包人提出的工程合同范围以外的零星工作，以计日工的形式计价；选项B，现场签证报告应当由承包人提交发包人；选项D，发包人对现场签证报告，逾期未确认也未提出修改意见的，应视为发包人已认可。参见教材P166。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]