[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107722,783,1,"单选题","某工程5月份工程款为800万元。合同约定当发生物价变化时，按照价格指数进行价格调整，项目施工至5月份起发生物价变化，其中人工费上涨5%，材料费中钢材价格上涨3%，其他项目价格未发生变化。人工费占工程款30%；材料费占50%（其中钢材占材料费的70%）；机械费占15%，其他项目占5%。则调整后5月份工程款是（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","700.3",false,{"key":16,"text":17,"correct":14},"B","775.1",{"key":19,"text":20,"correct":21},"C","820.4",true,{"key":23,"text":24,"correct":14},"D","944.0","考点:物价变化。800×[0.3×1.05\u002F1＋0.5×0.7×1.03\u002F1＋0.5×0.3＋0.15＋0.05]＝820.4（万元）。参见教材P167。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]