[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107721,783,1,"单选题","根据《建设工程量清单计价规范》（GB 50500－2013），工程发包时，招标人要求索赔的工期天数超过定额工期（ ）时，应当在招标文件中明示增加赶工费用。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","10%",{"key":19,"text":20,"correct":14},"C","15%",{"key":22,"text":23,"correct":24},"D","20%",true,"考点:提前竣工。根据提前竣工（赶工补偿）的有关规定，工程发包时，招标人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，将其量化；超过者，应在招标文件中明示增加赶工费用。参见教材P173。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]