[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107719,783,1,"单选题","在处理工程变更过程中，（ ）审查承包人提出的工程变更申请，提出审查意见，并对工程变更费用及工期影响做出评估。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总监理工程师",false,{"key":16,"text":17,"correct":14},"B","专业监理工程师",{"key":19,"text":20,"correct":14},"C","总监理工程师组织发包人.承包人",{"key":22,"text":23,"correct":24},"D","总监理工程师组织专业监理工程师",true,"考点:项目监理机构对工程变更的管理。总监理工程师组织专业监理工程师审查承包人提出的工程变更申请，提出审查意见，并对工程变更费用及工期影响做出评估。最为接近的选项C，应为总监理工程师组织发包人、承包人等共同协商确定工程变更费用及工期变化，会签工程变更单。参见教材P174。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]