[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107717,783,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）的规定，对于特殊反常的天气原因影响施工，承包人可以索赔（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":18},"B","工期+费用",false,{"key":20,"text":21,"correct":18},"C","工期+费用+利润",{"key":23,"text":24,"correct":18},"D","费用","考点:索赔的主要类型。由客观原因造成的延期，例如特殊反常天气等，承包人可得到工期补偿，但得不到费用补偿。参见教材P180。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]