[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107716":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107716,783,1,"单选题","在青藏铁路施工过程中发现文物、古迹，为解决此问题承包商花费了大量的时间和金钱，则承包商有权索赔（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用，但不包括工期和利润",false,{"key":16,"text":17,"correct":14},"B","费用和利润，但不包括工期",{"key":19,"text":20,"correct":21},"C","费用和工期，但不包括利润",true,{"key":23,"text":24,"correct":14},"D","费用.工期和利润","考点:索赔费用的计算。在施工过程中发现文物、古迹以及其他遗迹、化石、钱币或物品，则承包商有权索赔延长工期和费用的补偿，但不包括利润。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]