[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107712,783,1,"单选题","发包人核实承包人提交的竣工结算文件后，认为还需进一步补充资料和修改结算文件，则承包人在收到核实意见后的（ ）天内按照发包人提出的要求补偿相关资料并再次提交发包人复核。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","42","考点:竣工结算的程序。发包人应在收到承包人提交的竣工结算文件后的28天内核对。发包人经核实，认为承包人还应进一步补充资料和修改结算文件，应在上述时限内向承包人提出核实意见，承包人在收到核实意见后的28天内按照发包人提出的合理要求补充资料，修改竣工结算文件，并应再次提交给发包人复核后批准。参见教材P202。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]