[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107711,783,1,"单选题","发包人对工程质量有异议，拒绝办理工程竣工结算，已竣工未验收但实际已投入使用的工程，其质量争议应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按该工程的保修合同执行",true,{"key":16,"text":17,"correct":18},"B","根据具有相应资质的检测鉴定机构的检测结果确定解决方案",false,{"key":20,"text":21,"correct":18},"C","按工程质量监督机构的处理决定执行",{"key":23,"text":24,"correct":18},"D","由工程造价管理机构负责解释","考点:竣工结算的程序。发包人对工程质量有异议，拒绝办理工程竣工结算的，已竣工验收或已竣工未验收但实际投入使用的工程，其质量争议按该工程保修合同执行，竣工结算应按合同约定办理。参见教材P202。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]