[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107699,783,1,"单选题","下列关于预付款的说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","包工包料工程的支付比例不得高于签约合同价（扣除暂列金额）的10%",false,{"key":16,"text":17,"correct":14},"B","包工包料工程的支付比例不得低于签约合同价（扣除暂列金额）的30%",{"key":19,"text":20,"correct":14},"C","对重大工程项目，按月工程计划逐月预付",{"key":22,"text":23,"correct":24},"D","实行工程量清单计价的工程，实体性消耗和非实体性消耗部分应在合同中分别约定预付款比例（或金额）",true,"考点:预付款。包工包料工程的预付款的支付比例不得低于签约合同价（扣除暂列金额）的10%，不宜高于签约合同价（扣除暂列金额）的30%。对重大工程项目，按年度工程计划逐年预付。实行工程量清单计价的工程，实体性消耗和非实体性消耗部分应在合同中分别约定预付款比例（或金额）。参见教材P194。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]