[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107698":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107698,783,1,"单选题","（ ）是在某一时间已经完成的工作，以批准认可的预算为标准计算的资金总额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工作预算投资",true,{"key":16,"text":17,"correct":18},"B","计划工作预算投资",false,{"key":20,"text":21,"correct":18},"C","已完工作实际投资",{"key":23,"text":24,"correct":18},"D","计划工作实际投资","考点:赢得值法。已完工作预算投资为BCWP，是指在某一时间已经完成的工作（或部分工作），以批准认可的预算为标准计算的资金总额。参见教材P208。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]