[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107696,783,1,"单选题","某项目计划工作预算投资为50万元，已完工作实际投资为65万元，已完工作预算投资60万元，则投资偏差为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":21},"C","－5",true,{"key":23,"text":24,"correct":14},"D","10","考点:赢得值法。投资偏差＝已完工作预算投资－已完工作实际投资。依题意根据公式，投资偏差＝60－65＝－5（万元）。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]