[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107695,783,1,"单选题","在投资偏差分析中，可把投资偏差表示为（ ）与已完工作实际投资的差异。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工作预算投资",true,{"key":16,"text":17,"correct":18},"B","计划工作预算投资",false,{"key":20,"text":21,"correct":18},"C","未完工程计划投资",{"key":23,"text":24,"correct":18},"D","拟完工程计划投资","考点:赢得值法。投资偏差=已完工作预算投资-已完工作实际投资。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]