[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107694,783,1,"单选题","某工程施工至10月底，经统计分析，已完工作实际投资为260万元，已完工程预算投资为240万元，计划工作预算投资为200万元，则该工程此时的进度偏差为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","40",true,{"key":16,"text":17,"correct":18},"B","20",false,{"key":20,"text":21,"correct":18},"C","-20",{"key":23,"text":24,"correct":18},"D","-40","考点:赢得值法。进度偏差=已完工作预算投资-计划工作预算投资=240-200=40（万元）。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]