[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107692,783,1,"单选题","进行投资偏差分析时，当CV为负值时表示（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目运行超出预算投资",true,{"key":16,"text":17,"correct":18},"B","项目运行节支",false,{"key":20,"text":21,"correct":18},"C","项目进度延误",{"key":23,"text":24,"correct":18},"D","项目进度提前","考点:赢得值法。CV表示投资偏差，CV=已完工作预算投资BCWP-已完工作实际投资ACWP，当CV为负值时，表示已完工作实际投资大于已完工作预算投资，项目运行超出预算投资。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]