[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107691,783,1,"单选题","某工程的A分项工程施工至6月底，经统计分析得到，计划工程量为300立方米，计划单价为200元\u002F立方米；实际工程量为350立方米，实际单价为190元\u002F立方米。则分项工程A的进度偏差是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提前10000元",true,{"key":16,"text":17,"correct":18},"B","延误10000元",false,{"key":20,"text":21,"correct":18},"C","提前13000元",{"key":23,"text":24,"correct":18},"D","延误13000元","考点:赢得值法。BCWP＝350×200＝7（万元）；BCWS＝300×200＝6（万元）。SV＝7－6＝1（万元）。参见教材P209。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]