[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107690,783,1,"单选题","施工过程中，出现施工图纸变更导致项目特征与招标工程量清单项目特征描述不符时，综合单价的确定应以（ ）的项目特征为准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","原设计图纸所示",false,{"key":16,"text":17,"correct":14},"B","清单描述",{"key":19,"text":20,"correct":21},"C","变更图纸所示",true,{"key":23,"text":24,"correct":14},"D","标准图集描述","考点:项目特征不符。承包人应按照发包人提供的设计图纸实施工程合同，若在合同履行期间出现设计图纸（含设计变更）与招标工程量清单任一项目的特征描述不符，且该变化引起该项目的工程造价增减变化的，应按照实际施工的项目特征，按规范中工程变更相关条款的规定重新确定相应工程量清单项目的综合单价，并调整合同价款。参见教材P164。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]