[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107688":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107688,783,1,"单选题","2016年3月实际完成的某土方工程，按2015年3月签约时的价格计算的工程价款为2000万元，该工程的定值权重为0.2，各调值因子除人工费的价格指数增长了10%外均未发生变化，人工费占调值部分的50%。按调值公式法计算，该土方工程需调整的价格差额为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","40",{"key":19,"text":20,"correct":21},"C","80",true,{"key":23,"text":24,"correct":14},"D","100","考点:物价变化。物价变化引起合同价款调整时，如果影响因素较少、各因素的权重较大，可以采用如下公式： 。该土方工程需调整的价格差额=2000×[0.2+0.8×（0.5×1.1+0.5×1）-1]=80（万元）。参见教材P167。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]