[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107687,783,1,"单选题","由总承包单位或安装单位负责采购的设备，采购前应向（ ）提交设备采购方案，并按相关程序审查批准后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","总承包单位或安装单位技术负责人",{"key":23,"text":24,"correct":18},"D","项目监理机构","考点:物价变化。承包人应在采购材料前将采购数量和新的材料单价报发包人核对，确认用于本合同工程时，发包人应确认采购材料的数量和单价。参见教材P168。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]