[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107686,783,1,"单选题","由于工程师原因导致承包人自有的施工机械停工，一般应按（ ）计算索赔款额。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","台班实际租金",false,{"key":16,"text":17,"correct":14},"B","台班使用费",{"key":19,"text":20,"correct":14},"C","机械台班费",{"key":22,"text":23,"correct":24},"D","台班折旧费",true,"考点:索赔费用的计算。针对非承包人原因造成的停工，租赁设备执行实际租金（选项A）加分摊的进出场费；承包人自有设备执行台班折旧费（选项D），并非台班使用费或机械台班费（选项B或选项C）。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]