[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107685,783,1,"单选题","采用修正的总费用法计算索赔费用时，计算公式为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","索赔金额＝实际发生的直接费＋间接费＋利润",false,{"key":16,"text":17,"correct":14},"B","索赔金额＝实际总费用－投标报价估算总费用",{"key":19,"text":20,"correct":21},"C","索赔金额＝某项工作调整后的实际总费用－该项工作调整后的报价费用",true,{"key":23,"text":24,"correct":14},"D","索赔金额＝分部分项工程费＋利润＋税金","考点:索赔费用的计算。选项B，是总费用法的计算公式。修正的总费用法与总费用法相比，有了实质性的改进，它的准确程度已接近于实际费用法。参见教材P186。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]