[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107684,783,1,"单选题","计算索赔费用最常用的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总费用法",false,{"key":16,"text":17,"correct":18},"B","实际费用法",true,{"key":20,"text":21,"correct":14},"C","修正的总费用法",{"key":23,"text":24,"correct":14},"D","单价法","考点:索赔费用的计算。实际费用法是施工索赔时最常用的一种方法。参见教材P186。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]