[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1107682,783,1,"单选题","根据《标准施工招标文件》的索赔条款，当发包人要求承包人提前竣工，承包人可以要求的补偿内容是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工期",false,{"key":16,"text":17,"correct":14},"B","工期＋费用",{"key":19,"text":20,"correct":21},"C","费用",true,{"key":23,"text":24,"correct":14},"D","费用＋利润","考点:索赔费用的计算。根据《标准施工招标文件》的索赔条款，当发包人要求承包人提前竣工时，发包人仅补偿费用。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]