[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107681,783,1,"单选题","根据《标准施工招标文件》，对于因异常恶劣的气候造成施工单位的施工机械损坏和人员窝工以及相应的费用索赔，监理工程师应当（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","批准相应的施工机械损坏和人员窝工费用",false,{"key":16,"text":17,"correct":14},"B","批准相应的分部分项工程费",{"key":19,"text":20,"correct":14},"C","批准相应的措施项目费",{"key":22,"text":23,"correct":24},"D","不予批准",true,"考点:索赔费用的计算。根据《标准施工招标文件》，遇到特殊反常天气并造成了影响，承包人可以得到延长工期，但得不到费用补偿。参见教材P185。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]