[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107678,783,1,"单选题","某分项工程招标工程量清单为1000m3。施工中由于设计变更调整为1200m3。该分项工程招标控制价单价为300元\u002Fm3。投标报价单价为380元\u002Fm3。根据《建设工程工程量清单计价规范》，该分项工程的结算款为（ ）元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","430000",false,{"key":16,"text":17,"correct":14},"B","449000",{"key":19,"text":20,"correct":14},"C","442000",{"key":22,"text":23,"correct":24},"D","454250",true,"考点:工程量偏差。（1200-1000）\u002F1000=20%＞15%。380\u002F300＝1.27，偏差为27%，300×（1＋0.15）＝345（元），由于P0＝380（元）＞P2×（1＋0.15）＝345（元），该项目变更后的单价应调整为345（元）。工程结算款S=1.15Q0×P0+（Q1-1.15Q0）×P1=1.15×1000×380＋（1200－1.15×1000）×345＝454250（元）。参见教材P165。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]