[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107676,783,1,"单选题","某非招标项目，承包人报价值为2000万元，类似项目的合同价为1900万元。该项目承包人施工图预算为2050万元。则承包人报价浮动率是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2.44%",true,{"key":16,"text":17,"correct":18},"B","3.87%",false,{"key":20,"text":21,"correct":18},"C","5.00%",{"key":23,"text":24,"correct":18},"D","7.31%","考点:工程变更价款的确定方法。L＝1－2000\u002F2050＝2.44%。参见教材P176。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]