[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107675,783,1,"单选题","某工程因承包人原因致使原定竣工时间延误，延误期间内国家政策发生变化，由此引起的合同价款调整应遵循的原则是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调增的不予调整，调减的予以调整",true,{"key":16,"text":17,"correct":18},"B","调增和调减均予以调整",false,{"key":20,"text":21,"correct":18},"C","调增和调减均不予调整",{"key":23,"text":24,"correct":18},"D","调增的予以调整，调减的不予调整","考点:法律法规变化。法律法规变化是合同价款调整的常见原因之一。对于因承包人原因导致工期延误的，对照规定的调整（竣工）时间，在合同工程原定竣工时间之后，合同价款调增的不予调整，合同价款调减的予以调整（不利于承包人原则）。参见教材P164。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]