[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1107668,783,1,"单选题","发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的（ ），其余部分按照提前安排的原则进行分解，与进度款同期支付。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":18},"B","60%",true,{"key":20,"text":21,"correct":14},"C","80%",{"key":23,"text":24,"correct":14},"D","90%","考点:安全文明施工费。发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的60%，其余部分按照提前安排的原则进行分解，与进度款同期支付。参见教材P195。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]