[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1107667,783,1,"单选题","按子项目进行建设投资目标的分解时，一般可将建筑安装工程费用分解到（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设项目",false,{"key":16,"text":17,"correct":14},"B","单位工程",{"key":19,"text":20,"correct":14},"C","分部工程",{"key":22,"text":23,"correct":24},"D","分项工程",true,"考点:资金使用计划编制。对各单位工程的建筑安装工程投资还需要进一步分解，在施工阶段一般可分解到分部分项工程。分项工程是建设工程项目的最基本构成要素。参见教材P157。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]