[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107665,783,1,"单选题","根据《计价规范》的规定，下列计日工生效原则的描述中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人通知承包人后，承包人应予执行",true,{"key":16,"text":17,"correct":18},"B","承包人应在该项工作实施结束后的48小时内向发包人提交现场签证报告",false,{"key":20,"text":21,"correct":18},"C","发包人在收到承包人计日工报告后的7天内予以确认",{"key":23,"text":24,"correct":18},"D","发包人将一式三份确认的报告返还给承包人，作为计日工计价和支付的依据","考点:计日工。根据《计价规范》的规定，计日工生效原则包括：发包人通知以后，承包人应在该项工作实施结束后的24小时内向发包人提交现场签证报告（B有误）；发包人在收到报告后的2天内予以确认（C有误），并将其中一份返还给承包人（D有误），作为计日工计价和支付的依据。当然，其费用应按招标工程量清单中列出的项目、现场签证和填报的综合单价进行计算。参见教材P166。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]