[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107664,783,1,"单选题","某工程在施工过程中，因不可抗力造成损失，承包人及时向项目监理机构提出了索赔申请，并附有相关证明材料，要求补偿的经济损失如下：（1）在建工程损失30万元；（2）承包人的施工机械设备损坏损失5万元；（3）承包人受伤人员医药费和补偿金4.5万元；（4）工程清理修复费用2万元。根据《建设工程工程量清单计价规范》，监理人应批准的补偿金额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","32.0",true,{"key":16,"text":17,"correct":18},"B","36.5",false,{"key":20,"text":21,"correct":18},"C","37.0",{"key":23,"text":24,"correct":18},"D","41.5","考点:不可抗力。根据“各自损失，各自承担”的原则，因不可抗力导致的在建工程损失由发包人承担，工程所需清理、修复费用由发包人承担，因此，监理人应批准的补偿金额为30＋2＝32（万元）。承包人的施工机械设备损坏损失、承包人受伤人员医药费，均由承包人承担，不能索赔。参见教材P172。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]