[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1107663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1107663,783,1,"单选题","根据“计价规范”的规定，暂列金额由（ ）根据工程特点，按有关计价规定估算，施工过程中由（ ）掌握使用、扣除合同价款调整后如有余额，归（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人、发包人、发包人",true,{"key":16,"text":17,"correct":18},"B","发包人、监理人、发包人",false,{"key":20,"text":21,"correct":18},"C","监理人、监理人、发包人",{"key":23,"text":24,"correct":18},"D","监理人、监理人、监理人","考点:暂列金额。根据“计价规范”及有关规定，招标投标时，暂列金额由发包人根据工程特点，按有关计价规定估算；施工过程中（工程结算），由发包人掌握使用；扣除合同价款调整后如有余额，归发包人。参见教材P173。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]